Module 1 — The Fundamentals · 30 min
What Is a Project, and Why Do So Many Fail?
Monday morning, Yasmine starts her new job as project manager at a mutual health insurer with 220,000 members (a European nonprofit insurer, so the budgets in this course are in euros). Her assignment: Project Atlas, the overhaul of the member mobile app. At her first meeting, the head of member relations hands her a thick folder labeled "Compass." That was the previous attempt. Fourteen months of work, €300,000 spent, and an app that was never released. Nobody was incompetent, and yet the project failed. Before planning anything, Yasmine needs to understand why. That is the purpose of this lesson: define precisely what a project is, and identify the causes of failure that keep coming back from one organization to the next.
What sets a project apart from day-to-day work
An organization does two kinds of work. Operations are repetitive and ongoing: processing claims, answering calls, running payroll. A project is a temporary endeavor undertaken to produce a unique result. The major frameworks (PMI with its PMBOK, PRINCE2, the Scrum Guide for agile) phrase it differently, but they all share the same characteristics:
| Characteristic | What it means | Example on Atlas |
|---|---|---|
| Temporary | A defined start and end | Kickoff in January, go-live targeted within 9 months |
| Unique | The result does not yet exist in this form | A new app, not a minor update |
| Measurable objective | You can tell whether it succeeded | App store rating, fewer calls to the contact center |
| Limited resources | Budget, people and time are capped | A €480,000 budget, a team of about ten people |
| Uncertainty | Not everything is known at the start | The claims system APIs are poorly documented |
| Cross-functional | Several departments are involved | IT, member relations, compliance, marketing |
This distinction has a practical consequence: the methods that work for operations (procedures, stable productivity metrics) are not enough for a project. A project needs a clear scope, someone in charge, a plan and explicit management of uncertainty.
The triple constraint and quality
Every project constantly trades off three variables: scope (what you deliver), schedule and cost. They are often drawn as a triangle: if one moves, at least one other has to move too. Trying to add features without more time or budget always means paying with a fourth variable, quality, often invisibly at first.
%% titre: The project triple constraint %% narration: This diagram shows that scope, schedule and cost are linked to each other. When you force one without adjusting the others, quality, in the middle, pays the difference. flowchart TD P["Scope"] <--> D["Schedule"] D <--> C["Cost"] C <--> P P --> Q["Quality"] D --> Q C --> Q
The agile approach flips this triangle: schedule and cost are fixed (a stable team, fixed-length Sprints) and scope is what varies. We will come back to this in the next lesson. For now, remember that no method eliminates the trade-off: it only chooses which variable stays flexible.
The classic trap is to lock all three at kickoff, when you know very little. That is exactly what Compass did: 42 features, 10 months, €250,000, all decided before anyone had even analyzed the claims system.
Why so many projects fail
Studies published regularly on IT projects, such as the Standish Group's CHAOS reports, reach the same conclusion: only a minority of projects meet their planned schedule, budget and scope all at once. More interesting than the exact figure is that the causes are always the same. Yasmine reread the Compass meeting minutes and sorted them.
| Cause | Typical symptom | What happened on Compass |
|---|---|---|
| Vague objectives | Everyone has their own definition of success | "Modernize the app" with no measurable criterion |
| Absent sponsor | Decisions drag on or are never made | The sponsor changed jobs in month 4, with no replacement |
| Scope creep | Requests pile up and nothing is removed | From 42 to 67 features in 8 months |
| Missing users | The delivered product doesn't match real-world use | No member interviewed before month 11 |
| Imposed estimates | The deadline is set by management, not by analysis | Launch date announced to the steering committee before any estimate |
| Ignored risks | Known problems turn into crises | The claims API, flagged as fragile in month 2 |
| Poor communication | Bad news arrives too late | Status "green" until month 12, then an abrupt shutdown |
Notice that none of these causes is technical in the strict sense. The development work on Compass was of decent quality. The project failed on scoping, governance and communication. This is a constant: most failures are decided in the first few weeks, when you decide (or forget to decide) what you are building, for whom, and who makes the calls.
%% titre: How a project slides toward failure %% narration: This diagram shows the typical chain of events. A vague objective lets the scope balloon, the schedule slips, the variances get hidden, and the crisis erupts late, when there is no margin left. flowchart LR A["Vague objective"] --> B["Scope creep"] B --> C["Schedule slips"] C --> D["Variances not reported"] D --> E["Late crisis"] E --> F["Shutdown or degraded delivery"]
What success actually means
A successful project is not just a project "delivered on time." You need to distinguish three levels of success:
- Project management success: the deliverable is produced within the agreed schedule, cost and scope (or within accepted variances).
- Product success: the deliverable works and people use it. An app nobody downloads is a failure, even if it shipped on time.
- Business success: the result delivers the expected benefit. For Atlas, that means fewer calls to the contact center and higher member satisfaction.
The last two levels are often measured after the project ends. That is why objectives must be defined from the start with observable indicators. So Yasmine drafts a first version of Atlas's success criteria:
- average app store rating of at least 4.2 out of 5 (versus 2.1 today);
- a 25% drop in "where is my reimbursement?" calls within 6 months of go-live;
- 60% of medical receipts submitted through the app after 6 months;
- first release live within 9 months, within the €480,000 budget.
These criteria will be refined in Module 2. Their immediate value: they already make it possible to turn down requests that don't contribute to them.
Warning signs to watch from day one
An experienced project manager spots risky situations before they become problems. Here are the questions Yasmine always asks herself, and that will serve you on any project:
- Who is the sponsor, and do they have the authority to decide? Without an identified decision-maker, every trade-off becomes a negotiation.
- Can you write the objective in one sentence with a number in it? If not, scoping isn't finished.
- Was the date set before the estimate? If so, you need to know it and treat it as a major risk.
- Can you reach the future users? A project without access to its users is flying blind.
- What failed last time? The organization's history is the best source of risks.
On Atlas, two signals are red from the very first week: senior management has already publicly mentioned a launch "before the summer," and nobody in IT knows who actually understands the claims system API. Yasmine writes them down. She won't solve them today, but she will deal with them explicitly.
Hands-on practice
Pick a project you know: a current project in your organization, a past project, or, failing that, Compass as described above. In 20 minutes, produce a one-page sheet containing:
- One sentence explaining why this is a project and not an operation (at least three characteristics from the table).
- The variable of the triangle that was (or is) actually flexible, and the one that was supposed to be.
- The three most likely causes of failure or difficulty, each with an observed symptom.
- For each cause, one concrete action that could have been taken in the first month.
Expected deliverable: a three-row table (cause, symptom, preventive action) plus the two introductory sentences.
Show solution
Solution using the Compass case.
Why it is a project: Compass had a planned end (10 months), a unique result (a new app, not maintenance of the old one), a capped budget, and it involved several departments (IT, member relations, compliance).
Triangle: officially, all three variables were locked. In practice, the schedule gave way first (14 months without a release), then the scope was cut in a rush, too late. The variable that should have been flexible from the start was scope.
| Cause | Observed symptom | Preventive action in the first month |
|---|---|---|
| Vague objectives | "Modernize the app," no indicator | Have the sponsor approve 3 to 4 quantified success criteria |
| Scope creep | 42, then 67 features | Draw up an "out of scope" list and a rule: every addition removes an item of equivalent value |
| Ignored technical risk | Claims API flagged as fragile in month 2 | Run a 2-week technical study of the API before committing to a schedule |
Things to check in your own answer: a cause should be phrased as a mechanism ("the sponsor doesn't make decisions"), not as blame aimed at a person. A preventive action must be something the project manager can do, or propose to the sponsor, within the month. "Communicate better" is not an action; "a 30-minute weekly check-in with the sponsor, covering status and pending decisions" is.
Key takeaways
- A project is temporary, unique, resource-constrained and uncertain: it requires different management from day-to-day operations.
- Scope, schedule and cost are linked: forcing all three at once is paid for in quality.
- Failures come mostly from scoping, governance and communication, rarely from technology alone.
- Success is measured at three levels: project management, product and business benefit, with quantified criteria set from the start.
- Warning signs (weak sponsor, imposed date, missing users) can be spotted in the first week.